Current Status of Major Industrial Complexes

  • Home
  • Investment Projects
  • Current Status of Major Industrial Complexes

Recent paradigm shifts of the industrial complex

  • Increasing need for multi-functioning industrial complexes equipped with pleasant residential environment, research·education functions, and development for small or medium sized customized industrial complexes focused on enterprises
  • The role of industrial complexes changing fast into multi-functioning urban space, under the context of technology innovation and growing importance of industry-academic-and research cooperation


 이미지 크게보기

10 Completed industrial complexes [Total 41,389,000㎡ (Industrial Land 8,557,000㎡) ]

National Industrial Complexes(8) : Total area 38,770,000㎡ (Industrial facilities land: 6,711,000㎡)

DT V(4,270,000㎡), Daedeok Industrial Complex(3,195,000㎡), Daedeok Innopolis(25,579,000㎡), Jukdong•Shinseong•Banghyeon(1,468,000㎡), Munji(298,000㎡), Agency for Defense Development, etc.(3,960,000㎡)

General industrial complexes(2) : Total area 2,619,000㎡ (Industrial facilities land: 1,846,000㎡)

Daejeon industrial complex (2,317,000㎡), Haso (306,000㎡)

Daejeon's industrial complexes in the making

(Unit : 1,000 ㎡, KRW)
Daejeon's industrial complexes in the making
No. Name
(Location)
Total area of
Industrial complex
Industrial land
Area
Project overview
Implementer and project cost Duration
1 Seo-gu Pyeongchon Industrial Complex
(Seo-gu Pyeongchon-dong)
859 510 ㆍ Impemented by : Daejeon City Corporation
ㆍ Project cost : KRW 264.9 billion
2013~2024
2 Ansan Advanced Defense Industrial Complex
(Yuseong-gu Ansan-dong area)
1,591 477 ㆍ Implemented by : Public-private joint development
ㆍ Project cost : KRW 1.4 trillion
2015~2026
3 Jangdae Urban High-Tech Industrial Complex
(Yuseong-gu Jangadae-dong area)
73 34 ㆍ Implemented by : Korea Land & Housing Corporation
ㆍ Project cost : KRW 109.8 billion
2015~2025
4 Nano and Semiconductor National Industrial Complex
(Tuseong-gu Gyochon-dong)
5,296 2,312 ㆍ Implemented by : Korea Land & Housing Corporation, Daejeon City Corporation
ㆍ Project cost: KRW 3.458 trillion
2023~2030
5 Toplip/Jeonmin Business District
(Yuseong-gu Toplip-dong, Jeonmin-dong)
789 326 ㆍ Implemented by : Daejeon City Corporation
ㆍ Project cost: KRW 542.3 billion
2021~2028
6 Wonchon Advanced Bio Medical Innovation District 404 173 ㆍ Implemented by : Daejeon City Corporation
ㆍ Project cost: KRW 451.5 billion
2024~2029
7 SindongㆍDungok District
(Yuseong-gu, Sindong, Dungok )
3,445 1,176 ㆍ Implemented by : Korea Land & Housing Corporation
ㆍ Project cost : KRW 948.3 billion
2014~2024
8 Daedeok & Pyeongchon District
(Daedeok-gu, Pyeongchon-dong )
219 107 ㆍ Implemented by : Daejeon Metropolitan City(entrusted to: Daejeon City Corporation)
ㆍ Project cost: KRW 948.3 billion
2016~2025
9 Daejeon Industrial Complex (Fully accepted by LH)
( Daehwa-dong, Daedeok-gu)
99 59 ㆍ Implemented by : Korea Land & Housing Corporation
ㆍ Project cost : KRW 91.1 billion
2018~2024
10 Hannam Univ.Campus Innovation Park Urban High-Tech Industrial Complex 30 19 ㆍ Implemented by : Korea Land & Housing Corporation, Hannam University 2020~2025

Additional Industrial Complex Development Plan

* announced in 2024
대전의 조성중인 산업단지
No. Name
(Location)
Area Project overview
Implementer and Project cost Duration
1 Daedeok Innopolis Kendall Square 226,000㎡(approx. 70,000 pyeong) ㆍ Implemented by :(Phase 1)City Corporation (Phase 2)government-funded research institute
ㆍ Project cost : KRW 134 billion
2024~2028
2 Bonggok District Daedeok Innopolis K-Kendall Square 332,000㎡(approx. 100,000 pyeon) ㆍ Implemented by : Daejeon City Corporation
ㆍ Project cost : KRW 116.8 billion
2024~2029
3 Odong District 824,000㎡(approx. 250,000 pyeong) ㆍ Implemented by : Daejeon City Corporation
ㆍProject cost : KRW 232.7 billion
2024~2029
4 Sindae District 291,000㎡(approx. 90,000 pyeong) ㆍ Implemented by : K-Water
ㆍ Project cost : KRW 300 billion
2024~2029
5 Samjeong District 218,000㎡(approx. 70,000 pyeong) ㆍ Implemented by : Daejeon City Corporation
ㆍ Project cost : KRW 134.5 billion
2024~2029